OR Art. 370 -
Einleitung zur Rechtsnorm OR:
The Swiss Code of Obligations is a central code of Swiss civil law that regulates the legal relationships between private individuals. It includes five books that cover various aspects of contract law, law of obligations and property law, including the formation, content and termination of contracts, as well as liability for breach of contract and tort. The Code of Obligations is an important code of law for business and everyday life in Switzerland, as it forms the basis for many legal relationships and contracts and has been in force since 1912, whereby it is regularly adapted to social and economic developments.
Art. 370 OR from 2025
Art. 370 Approval of the work
1 Once the completed work has been expressly or tacitly approved by the customer, the contractor is released from all liability save in respect of defects which could not have been discovered on acceptance and normal inspection or were deliberately concealed by the contractor.
2 Tacit approval is presumed where the customer omits to inspect the work and give notice of defects as provided by law.
3 Where defects come to light only subsequently, the customer must notify the contractor as soon as he becomes aware of them, otherwise the work is deemed to have been approved even in respect of such defects.
Es besteht kein Anspruch auf Aktualität und Vollständigkeit/Richtigkeit.