Federal Act on the Amendment of the Swiss Civil Code (OR) Art. 366
Zusammenfassung der Rechtsnorm OR:
The Swiss Code of Obligations is a central code of Swiss civil law that regulates the legal relationships between private individuals. It includes five books that cover various aspects of contract law, law of obligations and property law, including the formation, content and termination of contracts, as well as liability for breach of contract and tort. The Code of Obligations is an important code of law for business and everyday life in Switzerland, as it forms the basis for many legal relationships and contracts and has been in force since 1912, whereby it is regularly adapted to social and economic developments.
Art. 366 OR from 2024
Art. 366 Prompt commencement and contractual production of the work
1 Where the contractor does not begin the work on time or delays its production in breach of contract or, through no fault of the customer, falls so far behind that there is no longer any prospect of completing the work on time, the customer is entitled to withdraw from the contract without waiting for the agreed delivery date.
2 Where during the production of the work it becomes evident that, through the fault of the contractor, the work will be produced in a manner that is defective or otherwise contrary to the contract, the customer may set the contractor or have the contractor set an appropriate time limit within which to take remedial action and notify him that any failure to do so will result in the hire of a third party to take such remedial action or to complete the work at the risk and expense of the contractor.
Es besteht kein Anspruch auf Aktualität und Vollständigkeit/Richtigkeit.