Federal Act on Public Procurement (PPA)

Zusammenfassung der Rechtsnorm PPA:



Art. 43 PPA from 2022

Art. 43 Federal Act on Public Procurement (PPA) drucken

Art. 43 Abandonment

1 The contracting authority may abandon the award procedure, particularly if:

  • a. it decides not to award the public contract for valid reasons;
  • b. no tender meets the technical specifications or the other requirements;
  • c. more advantageous tenders are to be expected due to changes in the framework conditions;
  • d. the tenders submitted do not allow for economical procurement, or significantly exceed the cost framework;
  • e. there are sufficient indications of an unlawful agreement affecting competition between the tenderers;
  • f. a significant change in the goods, work or services requested becomes necessary.
  • 2 Tenderers are not entitled to compensation in the event of a justified abandonment of the procedure.


    Dieser Gesetzesartikel ist im Jahr 2022 (prüfen Sie auf Aktualität) in Kraft getreten. Es besteht kein Anspruch auf Aktualität und Vollständigkeit/Richtigkeit. Wir verweisen Sie dazu auf www.admin.ch.